Primarvera scheduling support for a multi-year Arctic sealift program, connecting schedule development, progress measurement, forecasting, readiness, and management reporting.
A contractor supporting a future Arctic sealift program required a practical control structure for a long planning horizon, a rate-based commercial model, and multiple client, contractor, schedule, logistics, and readiness interfaces.
The scope did not carry a natural lump-sum earned-value basis, creating a need to separate useful physical-progress structure from stronger measures of forecast credibility, rate burn, readiness, and remaining exposure.
LPMS supported the planning and project-controls architecture for the sealift program, including the basis of schedule, progress measurement, management reporting and coordination structures required to carry the work toward execution readiness.
LPMS treated weighted progress as one reporting input rather than a complete management framework. The proposed structure connected physical advancement with readiness, forecast position, rate burn, commercial exposure, remaining-scope narrative, and decision cadence.
The engagement emphasized readable planning logic, defined ownership, and reporting that helped leadership interpret both movement and the conditions carrying the work.